Warksburn Catchment Project

Upper Warksburn, North Tyne

2,155 ha

8.8 km, source to Stonehaugh

PHASE 1

March 2026 – February 2027

Warks Burn

The work follows CaBA and Natural Flood Management principles, combining ecology, hydrology and landowner priorities. The project gathers the information needed to decide how to restore the natural functioning of the Warksburn, by:

Project Timeline

Outputs include a hydrological baseline report, sediment hotspot maps, a feasibility options matrix with indicative costs, a woodland creation study and a record of stakeholder engagement.

DeliverableDue
Monitoring programme initiation package. Land access, procurement log and asset register, baseline field survey and integrated baseline dataset.31 Aug 2026
Monitoring network commissioned and first data download. Calibrated, quality-assured network with a QA plan and first validated dataset.31 Aug 2026
Interim analysis brief. Flow regime and flashiness metrics, initial sediment dynamics review.30 Nov 2026
Catchment opportunities and stakeholder engagement summary. Sediment hotspot maps, feasibility shortlist and engagement log.31 Oct 2026
Final report. Integrated findings, methodology and limitations, and a ranked options matrix.31 Mar 2027

Northumbrian Water