Tuning the landscape: seeding Warksburn’s recovery
Twelve months of evidence-building, partnership and early recovery planning in the upper Warksburn, funded by the Reece Foundation, laying the groundwork for catchment-scale restoration.
11
Temperature loggers deployed
9
Priority opportunity areas mapped
£48,320
Follow-on Northumbrian Water funding
Aug 25 – Sep 26
Baseline phase

Why this project
Effective landscape recovery can’t be automated or standardised. It needs expert judgement, local knowledge and careful supervision over time. Reece Foundation seed funding let us build a decision-grade baseline for the Warksburn, a tributary of the North Tyne, before committing to large-scale intervention.
The work brought together ecologists, hydrologists, data scientists, academic partners and landowners around six aims: a robust baseline, an expert-led recovery framework, co-designed pathways with landowners, catchment-scale opportunity mapping, catalytic investment, and a model other catchments can reuse.
What we delivered
Monitoring network
Eleven Tinytag Aquatic 2 loggers deployed from January 2026, from the open upper reaches above Bluehemmel Lodge to the confluence area near Roses Bower Farm.
Baseline surveys
Field surveys across ecology, soil and hydrology, followed by spatial data analysis in spring 2026.
Recovery plan
A scoping plan for Haining Farm identifying nine priority opportunity areas, including a visual summary of the proposals.
Landowner platform
An in-house digital questionnaire and app that captured landowners’ priorities and fed directly into the plan.
What the water is telling us
Loggers were placed to capture two effects: the cooling influence of woodland shade, and the dilution effect of the Middle Burn joining the Warks Burn. Three stations form a transect along the burn.
| TT006 | Upper catchment, west of Bluehemmel Lodge. Sits between the other two sites, showing seasonal warming without TT001’s extreme peaks. |
| TT001 | Near Whygate. The most exposed reach: open valley, little riparian cover, the highest summer temperatures and largest daily swings, with peaks above 30°C in warm spells. |
| TT011 | Below Stonehaugh, downstream of the Middle Burn confluence. Cooler and more stable despite being furthest downstream, thanks to greater woodland shade and tributary dilution. |
Early evidence that riparian woodland and cool-water tributaries moderate summer temperatures. Strategic riparian woodland expansion and protection of cool tributaries could improve thermal resilience for brown trout (Salmo trutta) and wider river restoration. These findings are preliminary and will be tested with further data.
Monitoring was extended through August, the period of peak temperatures and lowest flow, so the baseline captures the catchment at its most stressed.
The Warks Burn Restoration and Nature Recovery Plan
Designed to work with the topography, hydrology and farming practice of Haining Farm, the plan joins up woodland, wetland, peatland, wildlife and heritage in a single strategy.
– Area 9 – Upland bog: rewetting through drain blocking and shallow pools to store water, slow runoff and cut downstream sediment.
– Areas 1 and 2 – Riparian buffers: 50–60 m native broadleaved corridors replacing plantation along the burn, stabilising banks and intercepting sediment.
– Area 4 – Valley floor: scattered broadleaves and scrub, with leaky barriers and temporary storage on flatter ground.
– Area 6 – Drained grassland: wader scrapes, shallow wetlands and seasonal ponds to hold water and support breeding birds.
– Area 7 – Grazing for wildlife: timed grazing to create nesting conditions for lapwing and curlew.
– Areas 3 and 5 – Orchards: blossom-rich habitat near the farm buildings for pollinators and community engagement.
– Area 8 – Heritage: conservation and interpretation of historic circular earthworks.
Landowner responses showed strong support for habitat management, ecological connectivity, species and peatland restoration, recreation and water quality, while keeping land productive. The plan is a collaborative vision, not a top-down proposal.
Planned vs delivered
| Activity | Status |
|---|---|
| Project initiation, partnerships and site access | Delivered |
| Baseline field surveys (ecology, soil, hydrology) | Delivered |
| Monitoring equipment deployment (January 2026, after calibration delay) | Delivered |
| Co-funding submissions and academic and community engagement | Delivered |
| Haining recovery plan drafting and scoping plan | Delivered |
| Haining plan finalisation and catchment opportunity mapping | Paused* |
*The plan is ready, but the landowner has not been able to take it forward. We will keep the dialogue open.
Leverage and recognition
- £48,320 secured from Northumbrian Water through the North Tyne Fine Sediment call, now continuing as the ROOTS project.
- AGRI-WISE application developed with the University of Salford and AI4Water: a £1.97 million, 30-month programme with a £1.44 million grant request.
- Forest Research visited in February 2026 as part of Woodland Water Code screening, which identified Warksburn as the most interesting catchment under consideration.
- Strategic partner invitation to the Resilient Rede and North Tyne Data and Evidence Working Group.
- Student placements drafted with the University of Salford, starting from 2027.
What comes next
Beaver-ready catchment
Preparing the conditions for a future licensed reintroduction, through riparian buffering, floodplain reconnection and local consent.
Living Lab
A long-term ambition to acquire land along the Middle Burn for a permanent research and teaching base.
Sustainable farming trials
Experimental farming on land at Crookbank, integrating production, habitat, soil health and water quality.
Species recovery
Habitat for water voles, otters, black grouse, hen harriers, white-clawed crayfish, pine marten and wildcat. Wild boar will be monitored through national policy first.
Haining Farm
Patient, renewed engagement to submit the completed recovery plan for consideration.
Education
Before-during-after monitoring data for schools, universities and research partners.
Funding and partners
This phase was funded by the Reece Foundation.

Its early backing gave the project the credibility to attract Northumbrian Water funding and to develop larger bids. Delivery partners and supporters include Northumbrian Water, the University of Salford, AI4Water, Forest Research and local landowners.
See also our Warksburn Catchment Project page.